ADU

California ADU cost 

  • ADU Cost: The total cost to build a 1200 sq ft, 3 bed, 3 bath detached ADU in Orange County, CA was approximately $285,000. This included architect fees, permit fees, planning fees, developer fees, labor, and all materials.
  • Cost Breakdown:
    • Architect Fees: $7,000
    • Planning Department Fees: $2,168
    • Public Works Fees (sewer, traffic, school): $8,056
    • Permit Fees: $678
    • Contractor Labor & Raw Materials: $212,000 (10% deposit, 20% upfront materials)
    • Materials (cabinets, solar, flooring, tile, fixtures, counters, etc.): The remaining amount, around $75,000.
  • Cost per Square Foot: Roughly $237 per square foot.
  • Timeline: The project took 21 months, from May 2021 (architect meeting) to January 2023 (certificate of occupancy). Permitting and planning took longer than construction.
  • Construction Timeline Highlights:
    • March 2022: Site prep, trenching, foundation.
    • April 2022: Foundation completion, underground work.
    • May 2022: Framing.
    • June 2022: MEP (Mechanical, Electrical, Plumbing).
    • July-August 2022: MEP inspection, house wrapping, drywall.
    • September-December 2022: Interior finishes, exterior landscaping, solar installation.
  • Key Takeaways:
    • Don’t stress over uncontrollable factors (e.g., rain delays).
    • Budget extra for unexpected costs and material price increases.
    • Treat workers with respect.
    • Use licensed, bonded, and insured contractors.
    • Have a clear draw schedule and contract.
    • Thoroughly interview contractors and establish a clear timeline and scope of work.
  • Rental Income: The ADU is projected to rent for approximately $4,200 per month (utilities included), generating about $50,000 annually.

Major ADU law changes in 2025.

  • AB 2533 (Amnesty for Unpermitted ADUs): Clarifies the legalization process for existing, unpermitted ADUs and JADUs. Key changes include:
    • Utilizing health and safety codes, not building codes, to determine if a unit is substandard.
    • Providing cities and counties with a checklist of requirements for permitting existing units.
    • Allowing homeowners to confidentially hire third-party inspectors to assess permit readiness without city reporting.
    • Eliminating impact fees, connection fees, and capacity charges if no new infrastructure is needed.
  • SB 1211 (Multifamily ADU Expansion): Significantly increases the number of ADUs allowed on multifamily properties. Starting January 2025:
    • One detached ADU can be built per existing unit on a multifamily property (up to a maximum of eight).
    • Reduced parking replacement requirements.
    • Clarifies that detached ADUs can be built in addition to interior conversions.
    • Expands the definition of livable space to include common areas.
  • SB 1077 (Coastal Zone ADUs): Aims to simplify the ADU permitting process in California’s coastal zone. This involves:
    • Creating a clearer process for obtaining ADU permits in coastal areas.
    • Requiring collaboration between the California Coastal Commission and the Housing and Community Development department to develop a standardized process for LCPs (Local Coastal Programs).
    • Holding a public hearing to determine the best policy for ADUs in coastal zones.
  • AB 1079 (CEQA Exemption for JADU Ordinances): Makes ordinances permitting JADUs exempt from the California Environmental Quality Act (CEQA).
  • SB 684 (Starter Homes and ADUs): Clarifies that ADUs do not count towards the 10-unit limit for streamlined starter home projects.
  • AB 2553 (Major Transit Stop Definition): Expands the definition of “major transit stop,” allowing for taller (18ft, two-story) ADUs in more locations. The change increases the allowable headway (time between buses) from 15 to 20 minutes.
  • Proposition 34 (Ballot Measure): Prevents organizations from using healthcare funds to finance housing ballot measures, potentially reducing the frequency of rent control propositions.
  • AB 2580 (Historic Designations and ADUs): Requires annual progress reports from cities and counties on housing permits, including those impacted by historic designations, potentially leading to more transparency and fewer project abandonments.
  • SB 937 (Impact Fee Timing): Delays the payment of impact fees to the issuance of a certificate of occupancy, making projects more affordable.
  • AB 1893 (Builder’s Remedy): May offer a legal recourse for homeowners facing delays in obtaining ministerial ADU permits from non-compliant cities and counties.
  • SB 1037 (Fines for Housing Obstruction): Imposes significant fines on cities that delay housing projects, potentially including ADUs if shot clock deadlines are missed; funds go directly to affordable housing within the offending jurisdiction.
  • SB 450 (SB9 Amendments): Introduces a 60-day shot clock for SB9 permit applications, requires detailed rejection reasons, and prevents cities from applying different zoning standards to SB9 units compared to other structures.
See also  Manhattan Beach

$45,000 LA ADU 

  • Strategy: The author built their Accessory Dwelling Unit (ADU) for $45,000 by acting as their own general contractor, hiring individual companies for specific tasks instead of one general contractor. This avoided the typical 40% markup associated with general contractor fees.
  • Cost Savings: Significant cost savings were achieved by:
    • Avoiding general contractor fees and markups.
    • Performing labor-intensive tasks themselves (insulation, trash removal, window installation, etc.).
    • Utilizing existing footings.
    • Strategic garage location minimizing plumbing and electrical costs.
    • Installing shear walls internally to avoid expensive exterior work.
  • Key to Success: Effective communication with the city inspector was crucial for obtaining necessary information and approvals. The author emphasizes the importance of asking clear, simple questions.
  • Contractor Experiences: The author shares negative experiences with contractors who withheld crucial information to inflate costs. This reinforces the value of their DIY approach.
  • Project Timeline: The project took approximately 4-5 months (November 2019 – March 2020), excluding the city’s lengthy permit process.
  • Future Plans: The author is developing a platform to simplify ADU construction for others, aiming to create a user-friendly process similar to building with Lego.

Five ADU planning essentials 

  • Sufficient Space: ADUs require a minimum square footage (at least 300 sq ft, even for studios). Consider the impact on your existing yard space, especially if renting the ADU.
  • Maximize Small Spaces: Design strategies like removing or visually eliminating walls (e.g., using bi-fold doors), large windows, and vertical storage significantly increase the perceived and actual size of a small ADU (even 500 sq ft).
  • Prioritize Storage: Clever storage solutions are crucial in smaller spaces. Built-in closets, maximized upper cabinets, and additional ledges help create a clean and efficient environment.
  • Don’t Skimp on Quality: While cost-effective strategies are important, investing in certain areas, such as the bathroom, creates a more luxurious feel, even in smaller spaces.
  • Embrace Natural Elements: Incorporating natural materials like wood can create a warm and inviting atmosphere, making the ADU feel more spacious and open.
  • ADU Regulations: Be aware of constantly evolving city and state ordinances regarding ADU construction and regulations.
  • ADU Benefits: ADUs offer diverse benefits such as multi-generational living, rental income, and a chance to rethink living spaces.